November 2026: Exciting progress taking shape

If you've driven by the future Arlington Medical Plaza recently, you've probably noticed that things are starting to look very different. 

One of the most exciting moments happened in October, when crews lifted the building's massive concrete wall panels into place. Known as "tilt-up" construction, the process is remarkably efficient and a little magical to watch. In just a matter of days, what had been a flat construction site suddenly began to look like a building, giving the community its first glimpse of what is to come. 

Construction continues to move steadily forward. Crews have completed most of the concrete curbs around the site, finished much of the final grading work, and installed drainage and foundation waterproofing systems that will help protect the building for years to come. Teams are also continuing work on the concrete panels in preparation for the next phase of construction. 

Another major milestone is just around the corner: A crane is scheduled to arrive mid-November, and structural steel deliveries will begin at the same time. Once steel starts going up, neighbors will see even more rapid changes as the Arlington Medical Plaza begins to rise. 

Thank you for following along and for your patience as we build this important new healthcare resource for our community.

Exterior view of a partially constructed three-story concrete building with window openings cut into the walls.

August 2026: Construction Update

Construction at the Arlington site has begun with the completion of the keystone retaining wall and installation of the water main. Excavation for the foundation and column pads continue. The concrete pour for the building foundations and column pads, as well as mechanical, plumbing and electrical below the slab will begin the week of August 10.

Construction crews install a concrete block retaining wall along an excavated site while an excavator pours gravel behind the wall.
Concrete foundation forms and reinforcing steel are in place across a large construction site as crews prepare for concrete pours. Excavated footings, wooden formwork, and gravel fill are visible throughout the future building footprint.

July 2026: Groundbreaking Ceremony

Skagit Regional Health, in partnership with Public Hospital District No. 3, Snohomish County, marked a significant milestone on Monday, July 7, 2026 with the groundbreaking of the Arlington Medical Plaza, a strategic investment in expanding convenient access to high-quality, patient-centered care in Snohomish County. The ceremony took place at the future site on East Medical Center Drive and brought together organizational leaders, clinicians, project partners and community stakeholders.

A group of approximately 14 people wearing hard hats stand in a line at a construction site, each holding a shovel in a ceremonial groundbreaking event.