HealthQuest Stories

Show Results For:
Clear Filters

Patient Stories

View All

Subscribe to Our
e-Newsletter

Subscribe

July Construction Update: Mount Vernon Surgery Center

Jul 17, 2023, 11:01 AM
The exterior of the Mount Vernon Surgery Center is coming together while the interior finishes near completion.
Exterior of Mount Vernon Surgery Center on sunny day

The construction site for the Skagit Regional Health – Mount Vernon Surgery Center continues to be a beehive of activity and daily change.

On the outside, landscaping featuring trees and shrubbery is under way and sidewalks are poured. The parking lot, including lighting and curbs, is taking shape and paving was scheduled for July 13 and 14.

The exterior of the building is nearing completion with all of the finishes and exterior signage will be installed in September.

Inside, permanent power went online in mid-June and three elevators will go online in August. Interior finishes, including paint, flooring and tile work is nearing completion on all three floors.

Operational walk-throughs continue to take place to assist with placement of accessories and equipment. Furniture installation will begin in August with medical equipment installation due by the end of October.

A reminder about some of the basics about the building:

Blog

458 posts

Last post : 09/29/2023

July Construction Update: Mount Vernon Surgery Center

Jul 17, 2023, 11:01 AM
The exterior of the Mount Vernon Surgery Center is coming together while the interior finishes near completion.
Exterior of Mount Vernon Surgery Center on sunny day

The construction site for the Skagit Regional Health – Mount Vernon Surgery Center continues to be a beehive of activity and daily change.

On the outside, landscaping featuring trees and shrubbery is under way and sidewalks are poured. The parking lot, including lighting and curbs, is taking shape and paving was scheduled for July 13 and 14.

The exterior of the building is nearing completion with all of the finishes and exterior signage will be installed in September.

Inside, permanent power went online in mid-June and three elevators will go online in August. Interior finishes, including paint, flooring and tile work is nearing completion on all three floors.

Operational walk-throughs continue to take place to assist with placement of accessories and equipment. Furniture installation will begin in August with medical equipment installation due by the end of October.

A reminder about some of the basics about the building: